A company permits a maximum wastage of 2% in its production process. During one month, wastage rises to 7%. The production manager investigates the c…
Practice question from Controlling (Class 12 · CBSE · Commerce Business Studies), with the correct answer and a step-by-step solution.
hard · MCQ · Q-4E35DD
A company permits a maximum wastage of 2% in its production process. During one month, wastage rises to 7%. The production manager investigates the causes and changes the machine-maintenance schedule. Which concept of controlling is illustrated most clearly?
- A.Management by exception, followed by corrective actionCorrect answer
- B.Delegation without accountability
- C.Planning without standards
- D.Coordination through informal communication only
Solution
The manager focuses attention on a significant deviation from the permitted standard, which reflects management by exception. Changing the maintenance schedule is corrective action intended to bring future performance back to the desired level.
More from Controlling
- Which of the following best describes the controlling function of management?
- A manager fixes a target of producing 10,000 units in a month. At the end of the month, actual production is found to be 9,200 units. What…
- Explain the relationship between planning and controlling in an organisation.
- A sales manager reviews every sales report but takes corrective action only when the deviation from the sales target exceeds 10%. Which pri…
Practise more Business Studies
Sign up free for adaptive practice on this chapter, with instant feedback and hints on every question.
Start practising freeFree to start · No credit card needed